A key drawback of Waterfall is…

Answer options

A
Late discovery of issues due to minimal early feedback
B
Too much customer collaboration
C
Overly rapid delivery
D
Excessive iteration

Correct answer: Late discovery of issues due to minimal early feedback

Explanation

Quick AnswerThe correct answer is Late discovery of issues due to minimal early feedback because it directly addresses the core logic of Software Engineering.