Burndown chart trending flat indicates:

Answer options

A
Constant progress
B
No remaining work
C
Little or no work completed
D
Scope reduced

Correct answer: Little or no work completed

Explanation

Quick AnswerThe correct answer is Little or no work completed because it directly addresses the core logic of Agile & DevOps.

Flat line means the remaining work isn’t decreasing, signaling issues.