Kanban limits WIP to:

Answer options

A
Increase multitasking
B
Improve flow and reduce cycle time
C
Force overtime
D
Match story points

Correct answer: Improve flow and reduce cycle time

Explanation

Quick AnswerThe correct answer is Improve flow and reduce cycle time because it directly addresses the core logic of Agile & DevOps.

This question has been retained as-is due to its unique context.