The main risk Spiral addresses early is…

Answer options

A
Project-specific major risks (tech, cost, schedule)
B
Grammar errors in docs
C
Color palette selection
D
Keyboard layout

Correct answer: Project-specific major risks (tech, cost, schedule)

Explanation

Quick AnswerThe correct answer is Project-specific major risks (tech, cost, schedule) because it directly addresses the core logic of Software Engineering.

This question has been retained as-is due to its unique context.