Which chart shows remaining work against time in a sprint?
Answer options
A
Burnup chart
B
Burndown chart
C
Gantt chart
D
Control chart
Correct answer: Burndown chart
Explanation
Quick AnswerThe correct answer is Burndown chart because it directly addresses the core logic of Agile & DevOps.
Burndown shows remaining work; burnup shows scope done vs total.