Which chart shows remaining work against time in a sprint?

Answer options

A
Burnup chart
B
Burndown chart
C
Gantt chart
D
Control chart

Correct answer: Burndown chart

Explanation

Quick AnswerThe correct answer is Burndown chart because it directly addresses the core logic of Agile & DevOps.

This question has been retained as-is due to its unique context.